Twin Buttes to Big Hill (McCamey D) Transmission Line Addition
Project Name: Twin Buttes to Big Hill (McCamey D) Transmission Line Addition
Project Location: From the Twin Buttes Substation located north of San Angelo, TX and Big Hill (McCamey D) station located in Schleicher County, TX.
Project Description: LCRA TSC will construct a new 38-mile, 345-kV transmission line between the Twin Buttes and Big Hill (McCamey D) substations in Tom Green and Schleicher counties.
Project Need: This project is a component of a broader CREZ Transmission Plan developed by ERCOT and approved by the PUC to integrate over 18,000 MW of renewable generation and deliver this energy to consumers in the most cost-effective manner. A number of transmission lines will provide transmission infrastructure necessary to meet the long-term needs of the growing area west of the I-35 corridor between San Antonio and Killeen.
Project Budget: $79.453 million
Project Map: Click to view larger image
View larger map.
Key Project Milestones:
  • Project Approved by LCRA Board: March 2009
  • Public Utility Commission Selects Route: July 2010
  • Project Engineering Complete: January 2012
  • First Access on ROW or Site: August 2010
  • Construction Start: December 2011
  • Construction Complete: December 2012
Need more project info?

For more information about this project, send your questions to Ask LCRA.

— Updated on February 7, 2012 at 02:17 PM —

 
 