Updating the 2015 Water Management Plan
LCRA is in the process of amending the 2015 Water Management Plan.
In 2018, LCRA held a series of meetings with LCRA customers and other interested groups to develop an amended plan. In December 2018, the LCRA Board of Directors approved changes to the plan.
On Feb. 28, 2019, LCRA staff submitted the application to amend the plan to the Texas Commission on Environmental Quality for approval. View the application.
The proposed Water Management Plan amendment:
- Maintains combined storage in lakes Buchanan and Travis above 600,000 acre-feet through a repeat of historic hydrology.
- Includes hydrology through 2016.
- Updates demands through 2025.
- Meets firm demands without shortage through a repeat of historic hydrology.
- Retains the current three-tier framework for interruptible agricultural curtailment that considers storage and inflow conditions, plus the use of a look-ahead test.
- Includes provisions to protect environmental flows.
Here are documents pertaining to the update process:
- Dec. 11, 2018, Amendments to the Water Management Plan approved by the LCRA Board of Directors
- Draft technical paper: Proposed methodology for identifying a drought potentially worse than a Drought of Record
- Draft technical paper: Development of ordered water versus diversion factors for Water Management Plan water availability modeling
- LCRA responses to comments received Oct. 25-Nov. 13, 2018
- LCRA responses to comments received Oct. 5-12, 2018
- LCRA responses to comments received Sept. 1-13, 2018
- Participant comments received Nov. 2-29, 2018
- Nov. 8 and Oct. 4, 2018, Water Availability Model results – Matagorda Bay salinity based on Colorado River modeled inflows
- Nov. 8, 2018, meeting presentation
- Draft Proposed WMP Revision: Environmental Flows (Updated Dec. 6, 2018)
- Draft Proposed WMP Revision: Interruptible Agricultural Curtailment (Updated Nov. 29, 2018)
- Draft Summary of Proposed Changes for 2018 WMP Application
- Nov. 8, 2018, Water Availability Model input files
- Nov. 8, 2018, Water Availability Model Monthly Output
- Nov. 8, 2018, Water Availability Model Results Summary
- Nov. 8, 2018, Water Availability Model results – additional detail on environmental flows
- Participant comments received Oct. 25-Nov. 1, 2018
- Overview of LCRA Water Supply Operations – August 2018
- Oct. 25, 2018, meeting presentation
- Oct. 25, 2018, Water Availability Model input files
- Oct. 25, 2018, Water Availability Model Monthly Output
- Oct. 25, 2018, Water Availability Model Results Summary
- Oct. 25, 2018, Water Availability Model results – additional detail on environmental flows
- Draft curtailment procedures for interruptible stored water in Oct. 25, 2018, WAM model
- Environmental Flow: Explanation of draft changes in the Oct. 25, 2018, WAM model
- Firm Yield Water Availability Model input files
- Draft technical paper: Development of combined firm yield of lakes Buchanan and Travis
- Participant comments received Oct. 4-12, 2018
- Oct. 4, 2018, meeting presentation
- Oct. 4, 2018, Water Availability Model input files
- Oct. 4, 2018, Water Availability Model Monthly Output
- Oct. 4, 2018, Water Availability Model Results Summary
- Oct. 4, 2018, Water Availability Model results – additional detail on environmental flows
- Draft technical paper: Assumptions underlying the Water Availability Model used to support
development of the LCRA Water Management Plan (Updated Nov. 28, 2018) - Participant comments received Sept. 1-13, 2018
- LCRA responses to comments received July 12- Aug. 31, 2018
- Sept. 6, 2018, meeting presentation
- Participant comments received Aug. 25-Aug. 31, 2018
- Participant comments received – as of Aug. 24, 2018
- Summary of approach used to model Arbuckle Reservoir operations in the July 12 and Aug. 10, 2018, WAM models.
- Aug. 10, 2018, Water Availability Model results – additional detail on environmental flows (Updated Sept. 5, 2018)
- Aug. 10, 2018, Water Availability Model input files
- Aug. 10, 2018, Water Availability Model Monthly Output
- Aug. 10, 2018, Water Availability Model Results Summary
- Draft curtailment procedures for interruptible stored water in Aug. 10, 2018, WAM model
- Environmental Flow: Explanation of draft changes in the July 12, 2018, WAM Model
- LCRA responses to comments received – as of June 22, 2018
- July 2018 Water Availability Model input files (replaced by Aug. 10, 2018, WAM input files)
- Water Demand Summary (2015 Water Management Plan, pending Water Management Plan update and 2020 Region K demands)
- Agriculture Demand Supplemental Information
- July 12, 2018, Water Availability Model Monthly Output
- July 12, 2018, Water Availability Model Results Summary
- 2014 Water Availability Model Results Summary
- July 12, 2018, meeting presentation
- Participant comments received – as of June 22, 2018
- Draft technical paper: Development of projected agricultural demands
- Draft technical paper: Development of projected firm demands for municipal and other firm uses (Updated July 2018)
- Draft technical paper: Development of projected firm demands for power plants
- Preliminary Projected 2025 Demands summary table – as of May 30, 2018
- May 21, 2018, meeting presentation
Questions, comments and requests to join the email list for updates should be submitted to [email protected].