North McCamey to Sand Lake Transmission Project - LCRA - Energy, Water, Community North McCamey to Sand Lake Transmission Project - LCRA - Energy, Water, Community




North McCamey to Sand Lake Transmission Project

LCRA TSC and Oncor are jointly proposing to build and operate a new 345-kilovolt transmission line to improve reliability and accommodate future demand and generating capacity growth in West Texas. The new transmission line is planned for portions of Crane, Crockett, Pecos, Reeves, Upton and Ward counties. It will connect LCRA TSC’s existing North McCamey Substation in Upton County with Oncor’s existing Sand Lake Substation in Reeves County, which are about 75 miles apart.

The project requires LCRA TSC and Oncor to amend their certificates of convenience and necessity (CCNs) with the Public Utility Commission of Texas. As part of the process, LCRA TSC and Oncor will seek input from state and local elected officials and various agencies to identify routing constraints to help determine potential locations for new transmission facilities and assess the project’s potential impacts. LCRA TSC and ONCOR will hold open houses for the public to learn more about the project and provide their feedback.

Latest Update – Jan. 24, 2023

Open house materials
LCRA TSC and Oncor hosted open houses Jan. 17-18 to share information with the public and answer questions about the project. Review information from the open houses below.

Example LCRA TSC transmission structure for proposed project.

Previous Project Updates

January 2023
Public open houses Jan. 17-18
Representatives from LCRA TSC, Oncor and Burns & McDonnell Engineering Company, the routing consulting firm, will be available to answer questions and discuss specific aspects of the project.

Jan. 17, 5-8 p.m.
Upton County 4H Community Center
18001 W. Hwy. 67, McCamey, TX 79752

Jan. 18, 4-7 p.m.
Reeves County Civic Center
1500 S. Cedar St. Pecos, TX 79772

Preliminary alternative route segments map now available
LCRA TSC and Oncor’s consultant, Burns & McDonnell Engineering Company, delineated the project study area and has begun data collection and constraint mapping. Click to view the alternative route segments map [PDF]. (Maps with more detail will be on view at the open houses.)

September 2022
The Electric Reliability Council of Texas’ (ERCOT) Board of Directors recently designated the project critical to reliability of the ERCOT system. Projects designated as “critical” are considered by the Public Utility Commission of Texas on an expedited basis. LCRA TSC and Oncor plan to file their joint CCN application by June 2023.

Project Timeline

2022
August ERCOT Board designates project as Tier 1 critical status
September-December LCRA TSC/Oncor identify preliminary alternate route segments
2023
January Public open houses Jan. 17 (Upton County Community Center) and Jan. 18 (Reeves County Civic Center)
Spring/Summer Expected filing of application for CCN amendments
Winter PUC decision and final route determination
2026
TBD Estimated project in-service date

Resources

Frequently asked questions [PDF]
Certificate process for transmission [PDF]
Interactive mapping tool: Zoom in and out on aerial imagery that depicts preliminary alternate transmission line route segments and property line information obtained from the county appraisal district. Note: High-speed internet is recommended.
Texas Landowner’s Bill of Rights

Contact

Justin Stryker, LCRA Senior Regulatory Case Manager
512-730-6803
[email protected]

Mr. Ifeoluwa Adetoro, Oncor
214-486-2093
[email protected]