Lakeway to Marble Falls Transmission Line Storm Hardening Project
LCRA Transmission Services Corporation is performing storm hardening on the 23-mile Lakeway-Marble Falls transmission line and other area transmission lines within the corridor.
The project will increase the reliability and safety of the structures and conductor by ensuring the transmission lines meet or exceed current National Electrical Safety Code and LCRA TSC design standards.
Latest Update – April 2024
Crews are performing construction work on transmission line segments from near the intersection of RM 620 and Stewart Road in Lakeway to west of SH 2322 and the Pedernales River in Spicewood. The construction work in the area is scheduled to be completed in late June.
Previous Project Updates
September 2023
Related vehicle activity will be concentrated on the east end of the project, going from Lakeway to Bee Creek, early September through November.
July 2023
Program Timeline
Summer 2023 |
---|
Construction activity begins on the eastern portion of project, Lakeway-Paleface, in Travis County. Clearing and excavation will continue into the Paleface-Marble Falls section, crossing into Burnet County, when east section is complete. |
September 2023-May 2024 |
Replacement of structures and conductor planned for Lakeway-Paleface section. |
Summer 2024 |
Right-of-way cleanup planned for Lakeway-Paleface section. Remaining excavation and clearing to be performed on the western portion of project, Paleface-Marble Falls. |
September 2024 – May 2025 |
Structures and conductor to be replaced on western portion of project, Paleface-Marble Falls. |
Summer 2025 |
ROW cleanup planned in Paleface-Marble Falls section. |
Contact
Please submit any questions using the Contact LCRA form.
Social Media